 Acciona Will Build The Jubail 3b Desalination  reverse osmosis system, including the civil works and  is expected to enter service sometime this year with
               the pumping of raw water.
                                                                 a treatment capacity of 450,000 m3/day, providing
 Plant, Its Sixth In Saudi Arabia  The project will include storage tanks for daily  a service to serve a population equivalent of two
               production, as well as a solar energy plant to reduce  million. It will also have a photovoltaic plant to reduce
               the consumption of power from the grid. To do this,  specific energy consumption.
 FINANCIAL CLOSURE  SWPC has announced the financial closure of the
 SWPC has announced the financial closure of the  project, which is estimated at US $ 692 million (612   ACCIONA will also build a photovoltaic solar plant.  ACCIONA was also awarded a 460-million turnkey
 project, which is estimated at US $ 692 million (612  million).  The EPC contract will also include the construction of  contract for the Al Khobar RO2 plant in Khobar, on the
 million)  The entry into service of the plant is planned for Q1   58 kilometres of power lines, an electricity substation  east coast of the country, around 400 kilometres from
 HIGH CAPACITY  2024, and it will be handed over under a 25-year BOO   and the associated marine works.  the capital Riyadh. This facility will have a capacity
 The plant will have a daily capacity of 570,000 m3 to  (Build-Own-Operate) agreement  of just over 630,000 m3/day, making it one of the
 supply 2 million people   With this contract, ACCIONA consolidates itself as one   REVERSE OSMOSIS  biggest in the country and the largest reverse osmosis
 LEADERSHIP  of the main water treatment infrastructure companies   A few months ago the publicly-owned Saline Water  plant in the world built under the EPC modality in a
 Once the plant is completed, ACCIONA will supply  in one of the areas with the highest water stress on   Conversion Corporation (SWCC) of Saudi Arabia  single phase.
 around 2.37 million m3/day of desalinated water in  the planet, the Middle East, and more specifically   awarded ACCIONA and its partner RTCC the design  In July 2018 the company was also awarded a contract
 Saudi Arabia using reverse osmosis technology.   Saudi Arabia. Once Jubail 3 is completed, ACCIONA   and construction of the Shuqaiq 1 desalination plant  for around 200 million for the construction and start-
 will supply around 2.37 million m3/day of desalinated   for US$384 million  (315 million). The plant, with a  up of the Al Khobar RO1 desalination plant, with a
 Together with its partner SEPCOIII, ACCIONA will  water using reverse osmosis, consolidating it as   daily capacity of 400,000 m3, will help to improve  capacity of 210,000 m3/day. Located near Al Khobar
 undertake the construction of the Jubail 3B desalination  the most efficient  and sustainable  desalination   drinking water supplies and offset the water shortages  RO2, it would provide a service to a population of 1
 plant. Its capacity of 570,000 m3/day will supply 2  technology with the smallest carbon footprint.  suffered by people living in south-western Saudi  million.
 million people in the cities of Riyadh and Qassim.  The plant will be located in the industrial city of Jubail   Arabia, providing a new source of drinking water for  It has also designed and built the above-mentioned
 ACCIONA and its partner are the main EPC contractors  on the Arabian Gulf  coast in eastern Saudi Arabia,   domestic, urban, agricultural and industrial use.  Al Jubail RO4 seawater desalination plant for Marafiq.
 in the project, which will be developed  and financed  around 100 kilometres from Dammam. ACCIONA   Last year, a 25-year, 530-million contract was  With a daily capacity of 100,000 m3, it serves both
 by a  consortium  consisting of  ENGIE, NESMA and  previously built the Jubail RO4 desalination plant   awarded for the design, construction, operation and  the city and the nearby industrial complex, in the east
 AJLAN for the publicly-owned Saudi Water Partnership  (capacity 100,000 m3/day) on the same site.  maintenance of the Shuqaiq3 desalination plant in  of the country.
 Company (SWCP).  ACCIONA will undertake the construction of the entire   the same area. It is currently under construction and