 Al Khawaneej Road  the remaining construction works, such that the  Roads (Al Khawaneej Roundabout) from 330 seconds

                bridge will be ready for opening by the end of March  to 45 seconds. It will double up the capacity of the
 Improvement Project reaches 60% completion  this year,» noted Al Tayer.  junction from 8,000 to 16,000 vehicles per hour.
                «The Improvement of Al Khawaneej Roads Project is  Replacing the roundabout at the intersection of Al

                one of the key strategic projects for improving the links  Khawaneej-Al  Amardi  Roads  by  a  surface  junction
                between Dubai and Sharjah through the improvement  will halve the waiting time from 120 seconds to 60

                of vertical roads linking with the Emirates Road and  seconds,» added Al Tayer.
                Sheikh Mohammed bin Zayed Road up to Airport  It also follows the opening of the Tripoli Street
                Street. The project will also accommodate the current  Improvement Project, providing a link between Sheikh
                and projected growth of traffic. Upon completion, it  Mohammed bin Zayed Road and Emirates Road. The

                will slash the travel time between Emirates Road and  opening of this 12-km road eased the traffic flow,
                Sheikh Mohammed bin Zayed Road from 25 minutes  improved  the  entry  points  at  Al  Warqa  and  Mirdif

                to 9 minutes, and the waiting time at the junction of  along Tripoli Road, and improved the overall safety
                Al  Khawaneej-Sheikh  Zayed  bin  Hamdan  Al  Nahyan  along the corridor.





























 Mattar  Mohammed  Al  Tayer,  Director-General,  closed section of the tunnel and is currently working

 Chairman of the Board of Executive Directors of the  on the supporting walls of the open section of the
 Roads and Transport Authority (RTA), announced that  tunnel. Works are expected to be completed and the
 the work on the Al Khawaneej Road Improvement  tunnel to be opened for traffic this March,» said Al
 Project is 60 percent completed.   Tayer.

 The project works include the construction of three  «Work progress rates also reached 60 percent on the
 intersections or service roads extending 23 km along  bridge leading to Al Awir, following the installation
 Al Khawaneej and Al Amardi Roads.  of precast bridge parts across Emirates Road in the

 «The completion rate reached 82 percent at the  direction of Abu Dhabi- Sharjah. Works are currently
 underpass intersection of Al Khawaneej Road and  underway for the installation of other parts at Al
 Sheikh  Zayed  bin  Hamdan  Al  Nahyan  Road.  The  Amardi, which are expected to be completed by the

 contractor completed the construction works at the  end of this month. Then the contractor will undertake